Florence Avenue Interchange Project – Week of Apr. 13 – Apr. 20, 2018

This project is 64% complete.
Projected date of completion for the Florence Ave. Bridge: Fall of 2018.
Project date for completion of project: Late 2019. 

 

Construction of retaining wall on west side of I-5 continues (below):

 

Grading and back-filling along the retaining walls on the east side of I-5 is almost complete. The next step is construction of sound walls. April 3 and April 10 (below):


The future Florence Ave. off ramp from northbound I-5 (below):

 