Florence Avenue Interchange Project – August 7, 2020 – August 14, 2020

This project is 92% complete.
Projected date of completion for the Florence Ave. Bridge and Project: *October 2020. Winter rains caused more delays. 

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Workers have been securing forms over rebar frames and pouring concrete for the new pedestrian walkway, traffic barrier, and median on the bridge. Photos below from August 7:

Video below from July 28:

Photos below  from July 14 & July 28

The Florence Ave. on ramp to northbound I-5, and the Florence Ave. off ramp from northbound I-5 will all remain closed until the second half of the Florence Ave. Bridge is complete. This is per request by the cities of Downey and Santa Fe Springs, to minimize traffic congestion until the three additional bridge lanes are provided to handle the increase in vehicles. Construction of the second half of the bridge is underway. 

 

 