I-5 NORTH Construction Advisory – SR-134 to Buena Vista Street, February 15-22, 2019

Work will occur during daytime hours unless otherwise noted. The schedule is weather-permitting and subject to change.

Construction Activities

SR-134 to Magnolia Boulevard

Sonora Avenue, Alameda Avenue, Western Avenue, Providencia Avenue, and LA River Bridges: Crews are working in the I-5 median to widen the bridges.

Providencia Avenue: Crews are installing fence barriers on the pedestrian bridge and constructing the median concrete barrier.

I-5 Median: Crews are installing drainage and constructing concrete piles for overhead sign structures at night and during the day. Crews are placing concrete pavement and constructing the median concrete barrier at night.

Magnolia Boulevard to Buena Vista Street

Northbound I-5 between Burbank Boulevard and Hollywood Way: Crews are removing pavement in the median during the day and at night.

I-5 Median: Crews have set up a crushing operation in the I-5 median near Walnut Avenue to produce aggregate base.

Empire Avenue: Crews are paving the on- and off-ramps and the new Empire Avenue.

Buena Vista Street: Crews are constructing an Austin Vault Sand Filter, a stormwater facility, next to the northbound off-ramp at Buena Vista Street.

Closures & Detours

SR-134 to Magnolia Boulevard

Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street Lane Closures: Intermittent daytime and nighttime street, ramp and lane closures on Alameda Avenue, Sonora Avenue, Western Avenue and South Flower Street through late 2019. Detours are posted.

Northbound and Southbound I-5 Lane Closures: Intermittent northbound and southbound lane closures between 10 p.m. and 6 a.m., at times reducing I-5 to one or two lanes in either direction.

Magnolia Boulevard to Buena Vista Street

Northbound and Southbound I-5 Lane Closures: Intermittent nighttime northbound and southbound I-5 lane closures, at times reducing I-5 to one or two lanes in either direction between Magnolia Boulevard and Hollywood Way from 9 p.m. to 6 a.m.

Buena Vista Street Closures: Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue.

On- and Off-Ramp Closures: Intermittent on- and off-ramp closures at Buena Vista Street, San Fernando Boulevard and Burbank Boulevard from 9 p.m. to 6 a.m.  Detours will be provided.

 

 