Valley View Ave. Interchange Project – May 17- May 24, 2019

Construction on this project is 40% complete.

Projected dates:
Completion of first half of Valley View Ave. Bridge: Revised to *late 2019.
Completion of second half of Valley View Ave. Bridge: Revised to *late 2021.
Firestone Blvd. reverts to two lanes in each direction at Valley View Ave.: End of 2021. 
I-5 Valley View Ave. Interchange project open to traffic: Revised to *End of 2021.

Also, please go to our Twitter page at twitter.com/My5LA for project updates.

Scheduled to be closed for a concrete pour on the Valley View Ave. Bridge:
From 8 p.m. Thursday, May 23 until 6 a.m. Friday, May 24.
Southbound Valley View Ave. from Alondra Blvd. to Arbor Pl.
Northbound Valley View Ave. from the railroad tracks south of I-5 to N. Firestone Blvd. 
Northbound traffic on Valley View Ave. may do a U-turn at Arbor Pl. Traffic on N. Firestone may turn right on Valley View Ave. to Alondra Blvd. 
Traffic will be open to all businesses south of Arbor Pl. 

Click to view videos of work in progress on I-5 Valley View Av. Bridge from May 14 below:

Panning north on center section of bridge with stem walls. Below, May 14:

The future Firestone Blvd. ramp to Valley View Ave. Bridge. Panning towards bridge where the ramp will connect. Below, May 14:

Where Firestone Blvd. ramp connects to the bridge. Below, May 14:

Workers installing rebar where future Valley View Ave. off ramp from southbound I-5 will connect to the bridge. Below, May 14:

This past week workers continued to prep the center section of the bridge for next week’s concrete pour. Photos below from May 7 & May 14:

On the future Firestone Blvd. ramp to the Valley View Ave. Bridge, the “soffit” (deck underside) and the “stem walls” along the edge are complete and the rebar frame has been installed. Photos below from May 14:

Workers continued installing rebar framework where the future Valley View off ramp from southbound I-5 will connect to the bridge in preparation for next week’s concrete pour. Photos below from May 7 and May 14: 

 